Home  |  News  |  Job Stories  |  San Francisco Development Whose Time Has Come

San Francisco Development Whose Time Has Come


The striking two-tower One Rincon Hill condominium project at the entrance to the San Francisco-Oakland Bay Bridge in San Francisco as it will look upon completion. The taller, 63-story tower is now under construction.

Interstate Concrete Pumping of Hayward, CA pumped 6,011 cu. yds. of concrete for the One Rincon Hill tower one mat pour February 4, 2006. Due to the highly space restrictive nature of the One Rincon Hill site and the difficulty of getting so many ready mix trucks to the project, Interstate used a combination of five Putzmeister boom pumps both on and off-site.



Interstate uses its Putzmeister BSA 14000 high pressure trailer pump to deliver the concrete from ground level to the waiting 34/38Z-meter placing boom atop the 63-story

One Rincon Hill is one of several placing boom jobs that Interstate and Webcor are currently working on in the San Francisco area.

Achieving a three-day pour cycle, the first on the west coast, Webcor Builders and Interstate Concrete Pumping are beating the clock on a typical five- to six-day schedule for each floor.

The One Rincon Hill condo project is using a combination of Putzmeister truck-mounted concrete boom pumps, a placing boom and high pressure trailer pump as well as a Thom-Katt® TK 50 for smaller jobs such as stairs.

The striking two-tower One Rincon Hill condominium project at the entrance to the San Francisco-Oakland Bay Bridge in San Francisco as it will look upon completion. The taller, 63-story tower is now under construction.

Interstate Concrete Pumping of Hayward, CA pumped 6,011 cu. yds. of concrete for the One Rincon Hill tower one mat pour February 4, 2006. Due to the highly space restrictive nature of the One Rincon Hill site and the difficulty of getting so many ready mix trucks to the project, Interstate used a combination of five Putzmeister boom pumps both on and off-site.



Interstate uses its Putzmeister BSA 14000 high pressure trailer pump to deliver the concrete from ground level to the waiting 34/38Z-meter placing boom atop the 63-story

One Rincon Hill is one of several placing boom jobs that Interstate and Webcor are currently working on in the San Francisco area.

Achieving a three-day pour cycle, the first on the west coast, Webcor Builders and Interstate Concrete Pumping are beating the clock on a typical five- to six-day schedule for each floor.

The One Rincon Hill condo project is using a combination of Putzmeister truck-mounted concrete boom pumps, a placing boom and high pressure trailer pump as well as a Thom-Katt® TK 50 for smaller jobs such as stairs.

San Francisco Development Whose Time Has Come

STURTEVANT, WI (May 1, 2007) – Times are changing on San Francisco’s Rincon Hill. Once home to the 183-foot Bank of America clock tower constructed in 1955, the prestigious site at First and Harrison streets and adjacent to the entrance to the San Francisco-Oakland Bay Bridge will change the city's skyline with a two-tower high-rise condominium development known as One Rincon Hill.

Ironically, this project is establishing a new construction benchmark by beating the clock. The combined efforts of the concrete contractor, San Mateo-based Webcor Builders and the concrete pumping company, Interstate Concrete Pumping of Hayward have achieved the first three-day floor cycle on the west coast.

Developed by Michael Kriozere of Urban West Associates headquartered in La Jolla and under the construction management of Bovis Lend Lease, groundbreaking on this $290 million project occurred in November of 2005 on the first of two elegantly slender towers. There will be 376 condominiums in the first tower with prices ranging from $600,000 for a small one-bedroom condo to $2.5 million for a penthouse.

Located near the city’s financial center, One Rincon Hill is one of several developments that are transforming San Francisco, bringing a new and high-priced lifestyle to a somewhat-run-down area. Some are calling it an instant landmark as it is the first thing people will see coming into the city from the East Bay.

A Tight Spot
The fact that the project is directly adjacent to San Francisco’s dramatic Bay Bridge made this project not only spectacular in terms of the views it will offer, it also made the logistics of getting concrete to the site a challenge.

Positioned near the entrance ramp for the bridge on a footprint of only 9,800 sq. ft., the 52- and 63-story two-tower condo project will reach 629 ft. when complete. “Since the buildings sit on less than an acre and a half of land, there are only about four feet between the first 63-story tower and the bridge,” says Interstate vice president and estimator for this job Andy Paulazzo. “While this location will be great for residents, it definitely posed issues in terms of how we would be able to get the concrete for the foundation on--site.”

Because the city of San Francisco would not grant a traffic lane for the ready mix trucks, Interstate came up with a plan to use five of its Putzmeister truck-mounted concrete boom pumps, both on- and off--site for the original mat pour. Starting early in the morning on February 4, 2006, the Interstate fleet began the 6,011 cu. yd. job.

“It was a very coordinated effort between our operators and the ready mix company,” notes Paulazzo. “On--site, we had a 58-meter pump on a steep ramp adjacent to the bridge’s on ramp, as well as a 52Z-meter over a corner and onto the mat. We also used our 42-meter to pump concrete into the hopper of a 46-meter down in the hole. In addition, we had a 55-meter off-site with its boom extended over a hill and onto the mat.”

Strength in Design
Based on bedrock, the concrete and steel foundation at One Rincon Hill is 12 ft. thick.
“For the mat pour,” says Paulazzo, “the pumps provided the reach we needed and took the concrete provided by Bode Gravel as fast as it could be delivered. Bode is the best. We have worked with them on numerous jobs and their mix designs always pump well and provide exactly what we need for a job.”

Bode provides several different mix designs for One Rincon Hill. This includes a
5,000-psi mix for the foundation and a combination of 8,000-psi and 6,000-psi for the core walls and columns. The post tension slabs are a 5,000-psi early strength mix that enables post tensioning in three days.

Designed for strength and stability in a notoriously unstable part of the country, the design of One Rincon Hill features a central core providing the main support for the structure as opposed to an exterior frame. Outside of the core, tall columns made of steel-reinforced concrete will function like outriggers to provide extra strength. Buckling restrained braces provide added seismic safety.

The first eight levels are for parking, providing the residential floors with vistas across the Bay and its famous bridge.

Placing Boom Expertise
Founded in 1996, Interstate Concrete Pumping has developed a strong industry following, especially in the use of placing booms. “Bucketing just eats up crane time,” says Jim Nolan, president of Interstate. “A placing system is much more efficient. Now, our competitors are catching on to this method.”

Ten years ago, Interstate and Webcor Builders started the age of the modern placing boom in San Francisco, when the two companies worked together on 388 Beal Street. “Placing boom jobs continue to grow in our area,” Paulazzo comments. “We work jobs with freestanding tower, outside tie-in and inside self-climbing, like One Rincon Hill. In fact, we recently had seven placing booms for Webcor on various projects at the
same time.”

“By using placing booms, we can keep the tower crane available for other critical tasks in the pouring cycle,” says Jack Harrington, Webcor’s concrete project manager. “The increased crane availability has been one of the key elements for achieving the historic three-day pace.”

Construction of One Rincon Hill is progressing quickly. Interstate is pouring a concrete floor every three days, compared to the usual standard in San Francisco, which is one floor every five to six days. “This three-day cycle will save 60 working days on the project, and the labor and material costs that go with it,” notes Harrington.

At the foot of the building, a 630 horsepower Putzmeister high pressure trailer pump delivers the concrete to the waiting 34/38Z-meter placing boom on 30 ft. of tower at the top of the structure, over 500 ft. above the summit of Rincon Hill.

The placing boom went up September 18, 2006 and the first tower should top off this August with a total of over 45,000 cu. yd. of concrete, including the mat pour.

The pumps and the placing system were all selected for their versatility and performance in maintaining the rigorous three-day schedule. “We have years of experience in pumping concrete,” says Paulazzo, “and knew we could rely on our equipment and operators like Al Valdez, Randy Boychuck and Robert Turner, Sr. to make this project happen in the 16 months we had to do it.”

In a typical three-day cycle, Interstate pumps the 160 cu. yd. core wall on day one. Day two starts early with a 230 cu. yd. deck pour in the morning followed by clean out and pouring another 50 cu. yds. for the columns in the afternoon. The third day is left open to prepare for the next deck.

From truck-mounted concrete boom pumps for the mat pour to powerful Thom-Katt®
TK 50s for small jobs like stairs, to its high pressure pump and placing boom system, Intestate has used practically every size pump in its Putzmeister fleet.

If all continues to go as planned, the building will be completed in April 2008 ready for occupants of the expensive condos with views over the city and beyond, from the Bay Bridge on the east to the Pacific Ocean on the west.