Home  |  News  |  Job Stories  |  Power Plant Construction Needs Powerful Equipment

Power Plant Construction Needs Powerful Equipment


Especially noteworthy is the placing boom's Multi-Z boom configuration, which proved exceptionally maneuverable in working under the low roof of a temporary overhead steel structure. The structure was specially built so construction could continue during the frigid winter months.

Instead of typical 5-inch pipe, 6-inch pipe was needed throughout the delivery system in handling the extremely harsh concrete mix. The brutal mix comprises crushed granite at 1.5-inches wide yet an inconceivable 4-inches long.

A BSA 2109 H-D trailermounted concrete pump serves as the main production unit being fed via a Putzmeister JT-5000 jumbo trough - a surge hopper directly flanged to the pump's hopper.The jumbo trough allows a quick and full discharge of the mixer trucks into its large capacity hopper.

The enormous Eastmain-1 dam project - underway in a desolate region in northern Québec - includes a powerhouse, a main dam across the Eastmain River, the spillway on the right bank of the river, and 33 dikes for reservoir closure. The largest of all structures being built is the 150-ft (50m) tall, 410-ft (125m) long and 180-ft (55m) wide powerhouse - where three huge turbines will generate the power.

To help place concrete more efficiently, Pompaction, Inc.of Pointe-Claire, Canada is supplying the concrete placing equipment for the major feat. Reliable equipment is vital, as Montreal is the closest inhabited area at over 750 miles (1200km) away.

Two Putzmeister placing booms are being utilized on site.They were originally standard MXR 34/38Z units modified by shortening the boom length to 30 meters to make up for the weight difference in using the 6-inch pipe required.

The major $108 million Canadian powerhouse, penstocks, and water intake project started in spring 2004 under the direction of Canadian contractor Aecon Hochtief. Upon completion in early 2006, over 60,000 cubic yards (46,000 m 3) of concrete will have been consumed for their contracted portion, which is about two-thirds of the total 89,000 cubic yards (68,000 m 3) needed for the entire project.

Especially noteworthy is the placing boom's Multi-Z boom configuration, which proved exceptionally maneuverable in working under the low roof of a temporary overhead steel structure. The structure was specially built so construction could continue during the frigid winter months.

Instead of typical 5-inch pipe, 6-inch pipe was needed throughout the delivery system in handling the extremely harsh concrete mix. The brutal mix comprises crushed granite at 1.5-inches wide yet an inconceivable 4-inches long.

A BSA 2109 H-D trailermounted concrete pump serves as the main production unit being fed via a Putzmeister JT-5000 jumbo trough - a surge hopper directly flanged to the pump's hopper.The jumbo trough allows a quick and full discharge of the mixer trucks into its large capacity hopper.

The enormous Eastmain-1 dam project - underway in a desolate region in northern Québec - includes a powerhouse, a main dam across the Eastmain River, the spillway on the right bank of the river, and 33 dikes for reservoir closure. The largest of all structures being built is the 150-ft (50m) tall, 410-ft (125m) long and 180-ft (55m) wide powerhouse - where three huge turbines will generate the power.

To help place concrete more efficiently, Pompaction, Inc.of Pointe-Claire, Canada is supplying the concrete placing equipment for the major feat. Reliable equipment is vital, as Montreal is the closest inhabited area at over 750 miles (1200km) away.

Two Putzmeister placing booms are being utilized on site.They were originally standard MXR 34/38Z units modified by shortening the boom length to 30 meters to make up for the weight difference in using the 6-inch pipe required.

The major $108 million Canadian powerhouse, penstocks, and water intake project started in spring 2004 under the direction of Canadian contractor Aecon Hochtief. Upon completion in early 2006, over 60,000 cubic yards (46,000 m 3) of concrete will have been consumed for their contracted portion, which is about two-thirds of the total 89,000 cubic yards (68,000 m 3) needed for the entire project.

Power Plant Construction Needs Powerful Equipment

Putzmeister equipment meets concrete placement demands of Eastmain-1 dam and powerhouse project

STURTEVANT, Wis. (May 1, 2005) – The on-going energy development of Hydro-Québec is part of a $2 billion project undertaken by SEBJ – Societe Energie de Baie James. For Hydro-Québec, SEBJ has been instrumental in the development of a very rich hydroelectric area via numerous power stations installed since the 1970s.

In particular, present construction of the new Eastmain-1 hydroelectric power plant – located on the Eastmain River near James Bay – is designed to generate 480 megawatt of electric power for Hydro-Québec.

The enormous project – underway in a desolate region in northern Québec – includes a powerhouse, a main dam across the Eastmain River, the spillway on the right bank of the river, and 33 dikes for reservoir closure. The construction of the project’s complex was broken down into five major contracts, awarded independently via open public bids.

The largest of all structures being built is the 150-ft (50m) tall, 410-ft (125m) long and 180-ft (55m) wide powerhouse – where three huge turbines will generate the power. This surface powerhouse, built into a rocky hill, is on the left bank of the Eastmain River. By the time the water exits through the tailrace, it will have dropped over 200-ft (60m) from the water intake. This head, combined with the flow, develops kinetic energy that causes the turbines and generators to turn, producing electricity.

In particular, the major $108 million Canadian powerhouse, penstocks, and water intake project were started in the spring of 2004 under the direction of Canadian contractor Aecon Hochtief. The Aecon Group is Canada's largest publicly traded construction company, and the group is 49%-owned by German construction giant Hochtief (parent of US-based Turner.)

Upon completion in early 2006, the reputable general contractor will have pumped over 60,000 cubic yards (46,000 m3) of concrete. This amounts to about two-thirds of the total 89,000 cubic yards (68,000 m3) needed for the entire project.

To help place concrete more efficiently, Pompaction, Inc. of Pointe-Claire, Canada is supplying the concrete placing equipment for the major feat. In particular, the contractor needs reliable equipment, as Montreal is the closest inhabited area at over 750 miles (1200km) away. Therefore if a machine fails in the job’s isolated location, it costs an exorbitant amount in down time.

Project Manager Ken Chryssolor of Aecon Hochtief said, “For over 30 years, I’ve worked on huge jobs within James Bay so I know how difficult the abrasive granite mix is to pump. As we needed high performance equipment that could handle the tough aggregate mix, we’re depending on all Putzmeister products.”

For the specific powerhouse and water intake project, the mix of equipment includes two BSA 2109 H-D high pressure trailer-mounted concrete pumps, a JT 5000 jumbo trough mixer, and two PM towers for mounting specially modified MXR 30Z-150 separate placing booms. The two Putzmeister placing booms were originally standard MXR 34/38Z units modified by shortening the boom length to 30 meters to make up for the weight difference in using the 6-inch pipe required.

Instead of typical 5-inch pipe, 6-inch was needed throughout the delivery system in handling the extremely harsh concrete mix supplied by the on-site batch plant. The brutal mix comprises crushed granite at 1.5-inches wide yet an inconceivable 4-inches long. Due to the abrasive mix, high pressures, and up to 500-ft (150m) pumping distances involved, Putzmeister ZX pipes and couplings are also being used.

Ken noted, “We needed heavy duty pipe and couplings for handling the extremely hard aggregate mix and for long usage life. Putzmeister’s special ZX pipe and couplings are completely leak-proof and high-pressure resistant. They definitely outlast any standard pipe and are an absolute necessity for this application.”

Two Putzmeister BSA 2109 H-D trailer-mounted concrete pumps were also selected because of their field proven S-valve for handling the coarse mix. They would also help keep wear costs to a minimum with their inherently long 83-inch (2100mm) stroke cylinders and up to 2205-psi (152 bar) high-pressure capabilities.

Without a set pattern, pumping occurs on an irregular basis. Average outputs range between 25 to 80 cubic yards an hour (20 to 60m3/hr) – with the rate of placement governed by the specifications and the complexity of the intricate forms, not by the equipment capabilities.

Of the two trailer pumps, one serves as the main production unit being fed via a Putzmeister JT-5000 jumbo trough – a surge hopper directly flanged to the pump’s hopper. The jumbo trough allows a quick and full discharge of the mixer trucks into its large capacity hopper, which in turn allows concrete to be fed to the pump at any speed needed from 0 to 125 cubic yards an hour (0 to 95m3/hr).

The second Putzmeister trailer pump serves as backup because cold joints are absolutely forbidden or the powerhouse would be structurally deficient. Consequently, in case of an equipment malfunction, the second pump can finish a pour.

Ken said, “We basically have to almost duplicate equipment needs because of our remote location 15 hours away from Montreal. With 600 men on a job, we can’t afford down time. Fortunately, no major problems have resulted to-date, and the equipment has performed to our demanding expectations.”

From April to November 2004, concrete work for the powerhouse took place. Two 75-ft (24m) tall placing boom towers were anchored with bolts and had to be precisely mounted in specified locations so no cold joints would interfere with the flow of water upon project completion.

The two placing booms – each using their full 100-ft (30m) horizontal reach – first provided full coverage to place concrete for both the walls of the huge turbines and the powerhouse structure itself.

In November, the two towers were moved to handle the intake structure. This time, they were supported by 15-ft by 15-ft by 4-ft high (4.5m x 4.5m x 1.2m high) poured concrete mats, and the placing booms still provided ample reach to all concrete placing areas.

Especially noteworthy is the placing boom’s Multi-Z boom configuration, which proved exceptionally maneuverable in working under the low roof of a temporary overhead steel structure. The structure was specially built so construction could continue during the frigid winter months.

Aecon Hochtief is also handling the horizontal concrete work for the penstocks. The three enormous penstocks are concrete-lined conduits excavated in the rock to channel water from the reservoir to the powerhouse turbines and are designed to maximize the head (drop in level). A Putzmeister BSA 2109 H-D trailer pump is pumping the concrete lining of these 350-ft (107m) long penstocks, each at a 25-ft (7.6m) diameter ranging from a 12-inch (305mm) to 4-ft (1.2m) thickness.

Besides the equipment’s proven performance, service and support capabilities were a significant factor in Aecon Hochtief selecting Pompaction for their equipment needs. Pompaction assisted in specifying the appropriate equipment, helped train operators, and is making service calls when deemed necessary.

And making service calls isn’t easy. As a closed site, entry is by invitation only via SEBJ (Air Creebec) aircraft or a 15-hour drive from Montreal. That’s why a specially developed workcamp was built to house construction site workers, who in staggering shifts work 42 days followed by a ten-day leave.

During a peak period last summer, nearly 2,400 workers were housed in dormitories. Similar to a mini-town, the site offers a variety of services such as cafeteria, hair salon, convenience store, post office and library along with indoor and outdoor recreational facilities. Once the project is complete, the approximate one-half square mile workcamp will be dismantled and transported to another job site.

Besides building the concrete intensive powerhouse, other construction projects on site are also utilizing various Putzmeister models, resulting in basically a monopoly of Putzmeister equipment on Eastmain-1. This includes a BSA 1409 electric-powered trailer pump being used by Norascon-Hebert, a joint venture between two established businesses in Quebec. The unit is competently placing concrete for all incline work associated with the penstocks.

In addition, a Telebelt® TB 105 belt conveyor was utilized for placing concrete on the main dam across the Eastmain River. The contractor, Hamel Construction of Québec City took full advantage of the conveyor’s special functionality to place unusually tough mixes and other aggregates such as sand, gravel and rock with ease.

For construction of the numerous dams, various Thom-Katt® trailer-mounted pump models were utilized for shotcreting by Norascon-Hebert and also by EDM Construction of Québec City, who were sub-contracted by CCDC in Montreal. In addition, a Putzmeister P-11 diesel-powered rotor/stator pump handled injection grouting for EBC, Inc. of Québec City.

Even the DynajetTM high-pressure washers – the latest addition to the Putzmeister America product line – were on-site working six months for Neilson Construction of Québec City. Next to the dam, two 500th models sprayed water at high 7,500-psi (520 bar) pressures to thoroughly clean selective areas of rock before concrete placement was possible.

In summary, Francis Gagnier, Vice President at Pompaction said, “We’ve sold several different pieces of Putzmeister equipment to various contractors working on this enormous and demanding project complex. That alone is valid testimony to the value placed on the equipment’s performance and reliability within such a remote location.”

As of spring 2005, the entire Eastmain-1 project was 66% complete. Plans are for the facility to be operational by late 2006.

SPECS
Concrete placing equipment dealer: Pompaction Inc. – Pointe-Claire (Montreal), Canada
General contractor for powerhouse and water intake structure: Aecon Hochtief
General contractor for penstocks: Norascon-Hebert – Québec, Canada
General contractor for Eastmain dam: EBC Inc.- Québec City, Canada
General contractor for spillway: Hamel Construction – Québec City, Canada
General contractor for dikes for reservoir closure: Neilson Construction, EBC Inc.,
CCDC (EDM Construction), and Fernand Gilbert Excavation