Grin and Bear It


Shown is the initial illustrative concept of the Pittsburgh Zoo's new Water's Edge exhibit when all three construction phases are completed in spring 2007.

Aerial view highlights the $14 million Water’s Edge construction project, which will make Pittsburgh one of only four zoos in the country to feature polar bears, walruses and sea otters in its collection.

The architect was given the complex task of incorporating the new structure into the existing aquamarine setting, which resulted in various construction challenges.

L&E Concrete Pumping of Pittsburgh is supplying Putzmeister boom pump models from 32 to 42 meters to meet important reach and setup requirements within the difficult terrain.

Built into the side of a steep hillside, the exhibit resulted in an irregular shape and the need for custom formwork.

Tight areas required a compact outrigger spread from the boom pumps to achieve efficient concrete placement.

With only an inch of clearance on each side, a horseshoe-shaped acrylic tunnel is lifted and precisely slid into a specially formed channel.

Shown is the initial illustrative concept of the Pittsburgh Zoo's new Water's Edge exhibit when all three construction phases are completed in spring 2007.

Aerial view highlights the $14 million Water’s Edge construction project, which will make Pittsburgh one of only four zoos in the country to feature polar bears, walruses and sea otters in its collection.

The architect was given the complex task of incorporating the new structure into the existing aquamarine setting, which resulted in various construction challenges.

L&E Concrete Pumping of Pittsburgh is supplying Putzmeister boom pump models from 32 to 42 meters to meet important reach and setup requirements within the difficult terrain.

Built into the side of a steep hillside, the exhibit resulted in an irregular shape and the need for custom formwork.

Tight areas required a compact outrigger spread from the boom pumps to achieve efficient concrete placement.

With only an inch of clearance on each side, a horseshoe-shaped acrylic tunnel is lifted and precisely slid into a specially formed channel.

Grin and Bear It

Overcoming Construction Challenges to Build Polar Bears a New Home

STURTEVANT, Wis. (September, 2006): This September, the Pittsburgh Zoo and PPG Aquarium welcomes back the most ferocious bear species on the planet – the amazing polar bears. Having departed in 1998, the bears are back by popular demand, returning to a special new home built during the first of three construction phases at the Zoo’s $14 million Water’s Edge exhibit.

The upcoming other two phases include a home for sea otters slated for completion by fall 2006 and a dwelling for walruses, anticipated next spring. When fully completed in April 2007, the exhibit will cover 2.8 acres and make Pittsburgh one of only four zoos in the country to feature polar bears, walruses and sea otters in its collection.

The architect, Indovina Associates of Pittsburgh, faced the complex challenge of incorporating Water’s Edge into hillside terrain while accommodating special exhibit requests and maintaining a natural flow throughout the display. Quite unique in its design, the unusual project made construction a complicated endeavor.

Unusual Exhibit Takes Shape
Using vast concrete forms, a multitude of machinery and several busy crews, the entire exhibit is taking shape under the expertise of Pittsburgh, Pennsylvania-based construction management company, Zambrano Corporation.

“The distinctive project involves many special characteristics for its construction,” says Brad Smith, Zambrano’s Project Manager. “This definitely isn’t your typical concrete structure.”

Rather unusual by today’s construction standards, all walls, beams and columns in the 22,000 sq. ft. structure are constructed entirely of concrete without any structural steel. This cast-in-place approach was specifically required for withstanding the harsh salt water environment.

Built within a steep 60 ft. embankment, the structure features an asymmetrical shape that makes concrete formwork and placement a challenge. Further adding to the task’s complexity, the project specifies construction of two highly unique acrylic tunnels serving as pedestrian walkways for viewing animals overhead. In addition, the job site’s location in the center of the zoo has meant working amidst hundreds of curious visitors each day.

Construction Team Formed
Zambrano's professional approach to construction includes working with a select group of sub-contractors who know the level of quality expected of them to make jobs run smoothly and without delays. Known and respected for its construction of parking structures and specialty projects within a five-state area, Carl Walker Construction of Pittsburgh was chosen as the concrete contractor for this unusual concrete placement job.

“The combination of terrain, footprint and location definitely proved challenging in safely and efficiently utilizing equipment and resources in this project’s concrete construction,” says Joe Racz, Project Superintendent of Carl Walker.

“The structure’s irregular shape required highly customized forms that we created in the field for an exact fit,” adds Racz. “Because we weren’t dealing with a square shape and typical right angles, placing the formwork and pumping the concrete was obviously more complicated.”

To ensure success in the intricate complexities of pumping the concrete, L&E Concrete Pumping of Pittsburgh is supplying Putzmeister boom pump models with reaches from 32 to 42 meters. It is estimated that these high performance units will pump over 5,000 cubic yards of concrete upon the project’s final completion date.

“Ironically, because the exhibit is so unique, it’s allowing our concrete pumps to exhibit their own unique features,” says Ed Femc, co-owner of L&E, an authorized Putzmeister distributor since 1989. “This includes the equipment’s compact outrigger spreads, highly maneuverable boom reaches and smooth free flow hydraulics when pumping.”

Donna Femc, L&E’s co-owner notes, “It’s a juggling act to ensure we schedule the perfect model size that provides both a small setup area yet still provides enough boom reach.”

Established in 1985, L&E has increased its concrete placing equipment fleet over the years to include 10 concrete pumps. The husband and wife team has established a large client base through their conscientious approach to service. The phone is personally answered 24/7 and the high quality machines are maintained by full-time service staff.

“All concrete pumps have performed flawlessly with absolutely no incidents to date,” says Racz. “Plus, L&E’s experienced operators have proven their invaluable skills by setting up in very tight spots and negotiating the boom into awkward areas to place concrete.”

Stone & Company of Greensburg, Pennsylvania is responsible for dispatching two different concrete mixes on this project. One is a typical 4,000 psi mix and the other is a special 5,000 psi micro silica mix that makes the concrete denser with fewer air pockets to withstand the long-term effects of the abrasive salt water against the concrete.

An Incredible View
The two 12 ft. wide acrylic viewing tunnels are shaped in a horseshoe configuration for a remarkable vantage point of animals as they swim under water. The first 30 ft. long tunnel, weighing 14,000 pounds, is a seamless design demonstrating the latest fusing technology. It provides an unobstructed view of the polar bears as spectators observe the animals in the 148,000-gallon pool overhead. A second 40 ft. acrylic tunnel, reputed to be the only one in the world for watching walruses, is being situated under a large 265,000-gallon pool.

“One of the most important aspects of the tunnel creation was the precise coordination required in constructing the sills to accurately match up with the huge acrylic covering,” says Smith. “It had to be exact, as we only had an inch clearance on each side.”

As a result, each tunnel was developed by fabricated channels, meticulously formed by hand on site. These were specifically designed so the enormous piece of acrylic could be lifted over top and slid into deep sills. The sills were later filled with grout and sealants for a tight seal.

Another special feature of Water’s Edge is the facility’s huge viewing windows. Similar to the approach used on the tunnels, field-fabricated concrete forms were required to create a sizeable 14 ft. square concave window area prior to installation of the five-inch thick plate glass. One window is for viewing the sea otters, and the other allows visitors to peer inside the air-conditioned polar bear den.

What’s on Exhibit?
Just as eye-catching as the Zoo’s animal inhabitants, the busy construction equipment often attracts crowds marveling at the cranes, boom pumps and mixers.

“It’s a little boy’s dream to watch these construction machines in action,” says Tracy Gray, Manager of Media and Public Relations for the Pittsburgh Zoo. “As a safety precaution, setup of the concrete boom pumps must occur early in the morning prior to zoo opening, and our security people escort each ready mix truck in and out of the zoo.”

“A sign by the construction site reads ‘Polar Bear Exhibit’,” says Dave Manculich, one of four L&E boom pump operators who have pumped on site. “However, people are more interested in the equipment pumping concrete, and the sign should say ‘Putzmeister Pump Exhibit’.”

The project started in March 2005, with over 3,000 cubic yards of concrete placed as of this summer. Half of the project still remains. Due to global warming, the U.S. Wildlife Federation is considering putting polar bears on the endangered list. So, although Water’s Edge has great public appeal, it is of vital significance to this species.

SPECS
Architect: Indovina Associates – Pittsburgh, PA
Construction manager: Zambrano Corporation – Pittsburgh, PA
Concrete contractor: Carl Walker Construction – Pittsburgh, PA
Pumping contractor: L&E Concrete Pumping, Inc. – Pittsburgh, PA
Ready mix supplier: Stone & Company – Greensburg, PA